The introduction of new Piccadilly line trains has been postponed by up to a year from the original schedule.
These 94 fully walk-through trains, equipped with air conditioning and CCTV, were initially set to be available for passenger travel in late 2025.
Transport for London (TfL) has now indicated that the launch is anticipated in the latter half of 2026.
TfL confirmed that testing for these trains will commence this summer. These next-generation trains will replace the outdated fleet from the 1970s.
The new models will be lighter, more eco-friendly, and feature real-time information displays and larger doorways. They are being hailed as the most intricate trains ever to be integrated into the Tube network.
TfL noted that some of the engineering hurdles stem from the Piccadilly line’s status as one of the longest and deepest on the network.
The complexity of the engineering tasks involved has proven to be more daunting than initially anticipated, contributing to the delay in their deployment.
Siemens Mobility in collaboration with TfL mentioned that testing could take up to a year, partly due to the aging tunnel infrastructure of a rail line that is nearly 120 years old.
Sambit Banerjee, Joint CEO of Siemens Mobility, expressed, “We regret that we cannot have our groundbreaking trains available for passengers sooner, but once they are operational, the advanced technology of these new trains will provide smoother, more sustainable, and more comfortable travel for Londoners for the next three decades or more.”